| Timber Frame Panel Erection : An example of the haste that a timber frame kit can be erected (whole kit was erected in just 1.30hours.) | ||||||
|
9:00AM - Soul plates ae fixed to carry the timber frame |
9:10AM - First panel is erected and temporarily braced |
9:20AM - Next Panel is fixed to first panel | ||||
|
9:25AM - Next Panel is fixed to second panel |
9:35AM - Next Panel is fixed to previous panel |
9:45AM - Next Panel fixed & more temporary bracing is applied | ||||
|
10:00AM - Next Panel is fixed, structure is nearly complete |
10:10AM - Next Panel is fixed, structure is nearly complete |
10:30AM - Kit is completly up in just 1.30 hours | ||||