Timber Frame Panel Erection : An example of the haste that a timber frame kit can be erected (whole kit was erected in just 1.30hours.)

9:00AM - Soul plates ae fixed to carry the timber frame

9:10AM - First panel is erected and temporarily braced

9:20AM - Next Panel is fixed to first panel

9:25AM - Next Panel is fixed to second panel

9:35AM - Next Panel is fixed to previous panel

9:45AM - Next Panel fixed & more temporary bracing is applied

10:00AM - Next Panel is fixed, structure is nearly complete

10:10AM - Next Panel is fixed, structure is nearly complete

10:30AM - Kit is completly up in just 1.30 hours

 